Minister Kondeva: The deadline for the construction of the National Children's Hospital is reduced by 9 months
06 June 2024
The deadline for the construction of the National Children's Hospital is being shortened by 9 months. We will make all necessary efforts to implement this priority project. The processes according to the schedule will run in parallel in order to accelerate the construction of the hospital as much as possible. This was stated by the Minister of Health, Dr. Galya Kondeva, at a joint briefing with the Deputy Prime Minister and Minister of Finance, Lyudmila Petkova, and the Executive Director of the Health Investment Company for Children's Hospital, Dr. Vlatko Gligorov.
The Minister of Health, Dr. Kondeva, has presented to the Council of Ministers the Updated Linear Schedule for the Accelerated Construction of the National Children's Hospital. In addition to making up for the accumulated delay of 7 months for clearing the terrain, Minister Kondeva also plans to shorten the deadlines for the construction and equipment of the hospital by 9 months, it became clear at the briefing.
100 million leva have currently been provided from the budget for the activities for the preparation of the National Children's Hospital, said the Deputy Prime Minister and Minister of Finance, Lyudmila Petkova. The state budget for 2025, as well as the Medium-Term Budget Forecast, will provide all the necessary funds for the design, construction, furnishing and equipment of the children's hospital, Deputy Prime Minister Petkova added.
Work is being carried out in parallel with the European Investment Bank and on the ground, thus optimizing the timeframe while complying with local legislation. After the stage of consultancy activities, the demolition of the buildings and the clearing of the terrain is completed, the next phase will begin.
In response to a journalistic question, Dr. Vlatko Gligorov said that they have managed to initiate the procedures under the ZTA for issuing a VISA for design, as well as the preparation of the coordination procedures with the operating companies - electricity, water supply, gas.
The main documents that will be needed to move to the architectural assignment are the structure and functional program of the children's hospital. The deadlines for the two assignments presented to the Ministry of Health by the EIB team are July 2024 and October 2024, respectively. Therefore, in November we are also starting the preparation of the public procurement for the design and supervision of the National Children's Hospital. All this is at the bank's suggestion, Dr. Gligorov specified. The orders will be announced after the release of the EIB's final report in January and will be in line with it, the executive director of ZIKDB was categorical. Nothing will be done at the expense of quality, but it will be the best for the health of our children, he added. With good organization and synchronization of activities, the deadlines for each stage of the project implementation can be further shortened, Dr. Kondeva was categorical.
-
Updated linear schedule for accelerated construction of 492
published on 16.12.2024
-
план-за-изграждане-оборудване-и-пускане-в-експлоатаци-494.pdf
published on 16.12.2024