HICCH managed to recover 8,564,804 leva from the deposit granted to DZZD "Children's Health" with an out-of-court settlement

21 December 2022

11.jpg

Thus, HICCH has recognized only the insurance costs, project study costs, costs for developing a task for amending the Detailed Development Plan (DDP) - Amendment to the Development Plan (DDP) and costs for developing projects for the Safety and Health Plan (SHP) and the Construction Waste Management Plan (CWMP) for the demolition of existing structures, implemented under the Engineering Contract No. RD-11-135/02.04.2020.

With the achievement of this agreement, a large part of the transferred deposit is refunded and the negative consequences of concluding the Engineering Contract No. RD-11-135/02.04.2020 are reduced, avoiding legal costs and payment of high state fees and charges.